Software Development Meeting 2011-Jul-18

Software Meeting Notes relevant to ezFIT 5.0 Milestones.

Attendees:

  • Barbara
  • Joel
  • AJ
  • Siegwart
Software Review
  • Side tracked with Audina website migration and server hardware failure.
    • Team asked to submit any issues with website, so that these get handled quickly, so we can get back soon to ezFIT5 project.
  • Started to add support for Noah 3.7 in ezFIT 5. Not had a chance to look into ExSilent's code yet.
  • Cleaning up user interface and debugging monaural fitting (Joel).
  • Barbara has been busy with CEU's for Aug 2011, so has not been albel to start esting ezFIT 5.
Completed Actions
Conclusion