Software Development Meeting 2011-Jun-20
Software Review
- Discussed the issues for supporting Noah 3.7 or 4.0 in ezFIT 5.
- Noah 4.0 would be ideal.
- Noah 3.7 could ensure all customers are covered during their transition to Noah 4.0.
- Discussed whether creating a Noah 3.7/4.0 wrapper for ezFIT 4.x makes sense.
- It buys time for Noah support.
- It could share some custom Noah libraries with ezFIT 5.
- It adds time to software development process.
- It would take away man-power from ezFIT 5 project.
- It cannot be certified by HIMSA. It is a non-conformant wrapper, something for temporary use.
- Discussed timeline for implementing ExSilent products in ezFIT 4.x.
- A minimum of 2 weeks, but more likely about 4 weeks.
Completed Actions
Conclusion
- Next meeting: Jun 23, 2011, 4pm