Software Development Meeting 2011-Jun-20
Software Meeting Notes
relevant to
ezFIT 5.0 Milestones
.
Attendees:
Steve
Joel
AJ
Siegwart
Software Review
Discussed the issues for supporting Noah 3.7 or 4.0 in ezFIT 5.
Noah 4.0 would be ideal.
Noah 3.7 could ensure all customers are covered during their transition to Noah 4.0.
Discussed whether creating a Noah 3.7/4.0 wrapper for ezFIT 4.x makes sense.
It buys time for Noah support.
It could share some custom Noah libraries with ezFIT 5.
It adds time to software development process.
It would take away man-power from ezFIT 5 project.
It cannot be certified by HIMSA. It is a non-conformant wrapper, something for temporary use.
Discussed timeline for implementing ExSilent products in ezFIT 4.x.
A minimum of 2 weeks, but more likely about 4 weeks.
Completed Actions
Conclusion
Next meeting:
Jun 23, 2011
, 4pm